Note: Assign contract baseline to Project Baseline and baseline updates (weekly/monthly) to Primary Baseline.
Columns

Selected Options:
- Activity ID
- Activity Name
- BL1 Duration
- BL1 Start
- BL1 Finish
- At Comp Dur (At Completion Duration)
- Start
- Finish
- Var – BL1 Dur (Variance – BL1 Duration)
- Var – BL1 Finish (Variance – BL1 Finish Date)
Filter

All of the following:
- Activity Status > is not equal to > Completed
Any of the following:
- Variance – BL1 Finish Date > is less than > -4d
- Variance – BL1 Duration > is less than > -4d
Group By

- WBS Level (Indent)
Sort By

- Field Name > Activity ID
- Sort Order > Ascending