When to apply this layout?
- Before and after moving the date to check unwanted programme movements (be sure to create pre baseline copy for comparison).
- To compare movement against the previous status update.
- For variance reporting/discussion with engineers.
Filter

All of the following:
- Activity Status > is not equal to Completed.
Any of the following:
- Variance – BL1 Finish Date > is not equal to 0d.
- Variance – BL1 Duration > is not equal to 0d.
Activity Columns

- Activity ID
- Activity Name
- BL1 Duration
- BL1 Start
- BL1 Finish
- At Completion Duration
- Start
- Finish
- Variance – BL1 Duration
- Variance – BL1 Finish
Group and Sort

Display options:
- Show Group Totals > YES
- Shrink vertical grouping bands > YES
Group By:
- WBS > Indent
Group By Options:
- Hide if empty > YES
- Name / Description > YES
Sort:

- Start > Ascending