P6 Layout: Lookahead

·

Use the following parameters:

  • Weekly report > consider a two-week (2W) lookahead.
  • Last Planner > consider a four-week (4W) or a six-week (6W) lookahead.
  • Monthly report > consider a one-month (1M) or a three-month (3M) lookahead

Filter

  • Activity Status > is not equal to Completed.
  • Start > is within range of Project Start (PS) and Data Date + number of weeks or months (DD+2W or DD+1M)

Activity Columns

  • Activity ID
  • Activity Name
  • Remaining Duration
  • Start
  • Finish
  • Activity Status
  • Activity Count (optional)

Group and Sort

Display options:

  • Show Group Totals > YES
  • Shrink vertical grouping bands > YES

Group By:

  • WBS > Indent

Group By Options:

  • Hide if empty > YES
  • Name / Description > YES

Sort:

  • Start > Ascending

Comments

Leave a Reply