P6 – Hours per Time Period

·

Go to Enterprise > Calendars.

  • Create/Select a calendar to modify
  • Set Time Periods for each calendar selected

Specify the number of work hours for each time period:

  • Hours/Day – set standard working hours per day (8hrs)
  • Hours/Week – multiply Hours/Day to number of working days per week (8×5=40hrs)
  • Hours/Month – multiply Hours/Day to the average working days per month (8×22=176hrs)
  • Hours/Year – multiply Hours/Week to 52 (40*52=2080hrs)

Average working days per month

  • 7 day work week – 30 days
  • 6 day work week – 26 days (30-4=26)
  • 5 day work week – 22 days (30-8=22)
  • 4 day work week – 18 days (30-12=18)

Comments

Leave a Reply