Go to Enterprise > Calendars.
- Create/Select a calendar to modify
- Set Time Periods for each calendar selected
Specify the number of work hours for each time period:
- Hours/Day – set standard working hours per day (8hrs)
- Hours/Week – multiply Hours/Day to number of working days per week (8×5=40hrs)
- Hours/Month – multiply Hours/Day to the average working days per month (8×22=176hrs)
- Hours/Year – multiply Hours/Week to 52 (40*52=2080hrs)
Average working days per month
- 7 day work week – 30 days
- 6 day work week – 26 days (30-4=26)
- 5 day work week – 22 days (30-8=22)
- 4 day work week – 18 days (30-12=18)